Maintenance Schedule
The following maintenance schedule must be followed to assure optimal working conditions of the system.
Printing Head Maintenance
Action | Frequency |
---|---|
Standard head nose cleaning | Continuous operation: Once per month or when sealing issues start to arise. Intermittent operation: before a shutdown of more than 3 days |
Deep head nose cleaning | Once every 3 months |
Prism cleaning | When required |
Stage Maintenance
Action | Frequency |
---|---|
Rail lubrication workflow | Once per month |
Stage maintenance | Once every 6 months |